Ankang No. 1 Road Phase II (Meigui Road to Antai Road)

Client: New Construction Office, New Taipei City Government

Project Description:

This project extends from Antai Road (Station 0+000) eastward, running roughly parallel to Section 3 of Ankang Road, ending at Meigui Road (Station 1+230). It connects seamlessly with the Phase I extension, spanning a total length of 1,230 meters. The new road aims to provide a fast connection to the Ankang Interchange and the Bitan area in Xindian, significantly alleviating congestion along Sections 1 to 3 of Ankang Road while distributing traffic across major intersecting roads, including Anzhong Road, Chezi Road, Qiaoxin Road, Anxiang Road, Meigui Road, Shuangcheng Road, and Antai Road.

Key Construction Elements:

  • Three-cell co-constructed tunnel
  • 11-span bridge over Shuangcheng Road (457 meters total length)
  • 5-span drainage bridge over Wuchong River tributary (163.8 meters total length)
  • 6-span MRT bridge over Shuangcheng Road (243 meters total length)
  • Box culvert retaining wall along Shuangcheng Road (72.35 meters total length)
  • Slope protection, drainage systems, roads, and utility relocation works

This project plays a crucial role in improving traffic efficiency and connectivity within the Ankang area.